Rainbarrow Farm Expansion Project

31 Jul 2020

SGNCS-Website---Image---Case-Study---Rainbarrow-Farm---7---expansion-project---2nd-upgrader-122528.jpg

We're pleased to announce completion of the capacity expansion project at Rainbarrow Farm.

In 2019 JV Energen commenced major upgrade projects at their Rainbarrow Farm AD plant to increase their capacity by 50% and the installation of carbon capture equipment.

In March 2020 we finalised phase one of the capacity expansion project which was the installation, commissioning and full integration of an additional biogas upgrader, including pre-treatment and propane injection equipment.

In July we returned to site and completed phase two and now the 'grid entry unit' (GEU) can fully accomodate the increased flows.